PMP考试每天一练-2018年PMP考试试题153
PMP考试试题一: Which of the following techniques helps to reduce bias in the data and keeps any individual having undue influence on the outcome? A.Delphi technique B.Brainstorming technique C.Interviewing technique D.Risk review technique 下列哪一项技术有助于减少数据偏见,并避免任何个人对成果产生不当影响? A.德尔菲技术 B.头脑风暴技术 C.访谈技术 D.风险审查技术 PMP答案解析:德尔菲技术,参考PMBOK PMP参考答案:A PMP考试试题二 To define the work package level of the work breakdown structure (WBS), what should the project team do? A.Analyze and identify all of the project deliverables and their associated work B.Organize and structure all of the project deliverables C.Decompose the project activities into their detailed components D.Analyze and identify all project activities, costs and durations 若要定义工作分解结构(WBS)的工作包层次,项目团队应该做什么? A.分析并识别所有项目可交付成果及其相关工作 B.组织和构建所有项目可交付成果 C将项目活动分解成详细的组成部分 D.分析并识别所有项目活动的成本和持续时间 PMP答案解析:制定了统计关系,可用参数估算 PMP参考答案:B |