PMP考试每天一练-2018年PMP考试试题141
PMP考试试题一: A company customizes products for a customer. Production begins and the quality team performs quality checks on all the products. After the products are approved, the customer receives the finished product. However, the customer is not satisfied with the quality and wants to send the products back.Which of the following techniques should be used to fix the issues? A.Quality control B.Control charts C.Process analysis D.Histogram 一家公司为一个客户定制产品。生产开始,质量团队对所有产品执行质量检查。产品获得批准之后,客户收到成品。但是,客户对质量不满意,想要将产品退回。若要解决这个问题应该使用下列哪一项技术? A.质量控制 B.控制图 C.过程分析 D.直方图 PMP答案解析:过程分析可以识别问题的根本原因 PMP参考答案:C PMP考试试题二 After a project is approved by the sponsor, a project manager is assigned. Which of the following should the project manager review first? A.Vendor contracts B.Approved project charter C.Approved project budget D.Customer requirements 在发起人批准项目后,任命了项目经理。项目经理应首先审查下列哪一项? A.供应商合同 B.批准项目章程 C.批准项目预算 D.客户需求 PMP答案解析:选项B的英文:Approved project charter,被批准的项目章程 PMP参考答案:B |