PMP考试每天一练--2016年PMP考试模考试题-6
6. Two project managers have just realized that they are in a weak matrix organization and that their power as project managers is quite limited. One figures out that he is really a project expediter and the other realizes he is really a project coordinator. How is a project expediter different from a project coordinator? A. The project expediter cannot make decisions. B. The project expediter can make more decisions. C. The project expediter reports to a higher-level manager. D. The project expediter has some authority. 6.两位项目经理认识到他们处于弱矩阵组织中,且权力非常有限。其中一位认为自己其实就是一名项目联络员,另一位则是一名项目协调员。项目联络员不同于项目协调员之处在于? A. 项目联络员不能做决定。 B. 项目联络员可以做很多决定。 C. 项目联络员向更高级经理汇报。 D. 项目联络员拥有一定权力。 参考答案:A 试题解析:组织结构特点(2.1.3) P22 |