PMP考试每天一练-2018年PMP考试试题63
PMP考试试题一: At the last minute, a project team implements a new feature that is not included in the scope statement. To obtain customer approval, what process should the project manager implement next? A.Plan Scope Management B.Validate Scope C.Perform Integrated Change Control D.Perform Qualitative Risk Analysis 在最后一刻,项目团队实施了范围说明书中未包含的新功能。若要获得客户的批准,项目经理下一步应执行哪个过程? A. 制定范围管理计划 B. 核实范围 C. 执行整体变更控制 D. 执行定性风险分析 PMP答案解析:得到客户的批准,正确的做法就是通过整体变更控制,也是四个选项中最好的参考答案。 PMP参考答案:C PMP考试试题二 To officially close a project, what should the project manager do? A. Close out the risk register B. Validate scope C. Update the project management plan D. Close out procurements 正式收尾项目时,项目经理应该怎么做? A.关闭风险登记册 B.核实范围 C.更新项目管理计划 D.结束采购工作 PMP答案解析:正式收尾项目时,应该先做确认范围 PMP参考答案:B |