PMP考试每天一练-2018年PMP考试试题47
PMP考试试题一: The customer of a delayed project requests an additional feature. The feature can be built with no significant impact to the schedule or cost.What should the project manager do next? A.Accept the proposal as compensation to the customer for the project delay B.Deny the request immediately without further consultation C.Put the feature on hold, as a future enhancement D.Create a change request and submit to the change control board for consideration 某个延期项目的客户请求增加功能。该功能可以在不对进度或成本产生重大影响的情况下嵌入。项目经理下一步该怎么做? A.接受该提议作为对客户项目延期的补偿 B.在不进一步咨询的情况下,立即拒绝该请求 C.搁置该功能,作为未来改进功能 D.创建一份变更请求,并将其提交给变更控制委员会考虑 PMP答案解析:直接接受、直接拒绝、搁置,都是不对的,排除ABC。应该遵循变更管理流程首先提交变更请求 PMP参考答案:D PMP考试试题二 The management team identifies a new risk that could potentially delay to a deliverable by six weeks. In response to this, what should the project manager do first? A. Quantity the impact B. Analyze the variance C. Update the risk register D. Implement corrective actions 管理团队识别可能会延迟某个可交付成果六周时间的新风险。为应对这种情况,项目经理应该首先做什么? A. 量化影响 B. 分析偏差 C. 更新风险登记册 D. 执行纠正措施 PMP答案解析:识别到新风险,首先应该更新到风险登记册中 PMP参考答案:C |