PMP考试每天一练-2018年PMP考试试题24
PMP考试试题一: A project manager wants to manage local market uncertainties for a project using the critical chain method (CCM), where should the project buffer be allocated? A.At intervals anywhere in the critical chain B.At the end of the critical chain C.At the beginning of the critical chain D.At the end of a sequence of tasks that leads into the critical chain 项目经理想要使用关键链法(CCM)管理一个项目的本地市场不确定性。应该在哪里分配项目缓冲? A.在关键链任意位置间隔 B.在关键链末端 C.在关键链的开始 D.在导致进入关键链的任务序列末端 PMP答案解析:PMBOK 178页:放置在关键链末端的缓冲称为项目缓冲,用来保证项目不因关键链的延误而延误。 PMP参考答案:B PMP考试试题二 A project manager negotiates contract terms with an external vendor that will provide additional resources to complete a critical project task. To minimize project risk, what type of contract should the project manager select? A.Cost-reimbursable B.Firm-fixed-price C.Fixed-price-incentive-fee D.Time and material 项目经理与将提供额外资源完成关键项目任务的外部供应商协商合同条款。为了减少项目风险,项目经理应选择什么合同类型? A.成本补偿合同 B.固定总价合同 C.总价加激励费用合同 D.工料合同 PMP答案解析:减少风险,对甲方有利的合同是总价合同 PMP参考答案:B |