PMP考试练习题一: At a stakeholder meeting, it is identified that the stakeholder group should include a community based organization (CBO). The project manager is concerned that there will be a lack f executive support for the inclusion of the CBO.What should the project manager do first? A. Send the CBO periodic updates B. Initiate perform integrated change control process C. Inform executives that the CBO will be included D. Expand regular project status communications to include the CBO 在干系人会议上,确定干系人团体应包含一个以社区为基础的组织(CBO)。项目经理担心包含CBO将缺少执行者的支持。项目经理首先应该做什么? A.向CBO定期发送更新情况 B.开始执行整体变更控制过程 C.通知执行者,将包含CBO D.扩大常规项目状态沟通范围,包含CBO PMP答案解析:因为涉及到高管层的意见,建议选B PMP参考答案:B PMP考试练习题二: A team of four sponsors gives a project charter to the project manager. In addition to the project manager, the project team consists of seven members from different functional groups.What is the number of communication channels? A.4 B.21 C.55 D.66 由四名发起人构成的团队向项目经理提供了一份项目章程。除了项目经理以外,项目团队由来自不同职能组织的七名成员组成。沟通渠道总数有多少? A.4 B.21 C.55 D.66 PMP答案解析:(4+1+7)*(4+1+7-1)/2=66 PMP参考答案:D |