At a stakeholder meeting, it is identified that the stakeholder group should include a community based organization (CBO). The project manager is concerned that there will be a lack f executive support for the inclusion of the CBO.What should the project manager do first?

A. Send the CBO periodic updates

B. Initiate perform integrated change control process

C. Inform executives that the CBO will be included

D. Expand regular project status communications to include the CBO

在干系人会议上,确定干系人团体应包含一个以社区为基础的组织(CBO)。项目经理担心包含CBO将缺少执行者的支持。项目经理首先应该做什么?

A.向CBO定期发送更新情况

B.开始执行整体变更控制过程

C.通知执行者,将包含CBO

D.扩大常规项目状态沟通范围,包含CBO

PMP答案解析:因为涉及到高管层的意见,建议选B

PMP参考答案:B

PMP考试练习题二:

A team of four sponsors gives a project charter to the project manager. In addition to the project manager, the project team consists of seven members from different functional groups.What is the number of communication channels?

A.4

B.21

C.55

D.66

由四名发起人构成的团队向项目经理提供了一份项目章程。除了项目经理以外,项目团队由来自不同职能组织的七名成员组成。沟通渠道总数有多少?

A.4

B.21

C.55

D.66

PMP答案解析:(4+1+7)*(4+1+7-1)/2=66

PMP参考答案:D

阅读本文的人还阅读了:
苏州PMP培训哪个好?几大热门苏州PMP培训机构对比
成都PMP培训哪个好?几大热门成都PMP培训机构对比
西安PMP培训哪个好?几大热门西安PMP培训机构对比
PMBOK第六版下载地址
PMP培训是什么?
PMP培训证明是什么?

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库