PMP考试每天一练-2018年PMP考试试题6
PMP考试试题一: The company requires a specific service for a project, but the capability does not exist within the project team. Which of the following documents should be used to find a vendor which provides the best service, price, and minimal risk? A.Request for information B.Request for proposal C.Statement of work D.Procurement management plan 公司要求对某个项目提供特定服务,但是项目团队不具有这个能力。为了找到能够提供最佳服务、价格和最小风险的供应商,应该使用下列那一项文件? A.信息邀请书 B.建议邀请书 C.工作说明书 D.采购管理计划 PMP答案解析:采购管理计划描述了如何识别预审合格的卖方、如何管理多个供应商。 A和 B是采购文件,C工作说明书是根据合同而定义的采购范围。 PMP参考答案:D PMP考试试题二: A business analyst collects requirements for a new project. Stakeholders are from different departments and have various requirements. The project budget is limited and can only deliver half of the requirements A.Facilitated workshops B.Focus groups C.Group decision making techniques D.Group creativity techniques 业务分析员为一个新项目收集需求。干系人来自不同部门并且需求也各不相同。项目预算有限只能交付一半需求。为确保应包含那些需求,业务分析员应使用下列哪一项? A.引导式讨论会 B.焦点小组 C.群体决策技术 D.群体创新技术 PMP答案解析:跨职能、跨部门收集需求。 PMP参考答案:A |