PMP考试试题一:

The project manager conducts an inspection with the customer to confirm that the project deliverables meet the product acceptance criteria and fulfill thecustomer’s expectations.These actions are part of which of the following processes?

A.control quality

B.close project or phase

C.Control scope

D.Validate scope

项目经理与客户一起进行检查,确认项目可交付成果是否符合产品验收标准并满足客户的期望。这些行动都属于下列哪一个过程的组成部分?

A.控制质量

B.项目或阶段收尾

C.控制范围

D.核实范围

PMP答案解析:根据题干PM与客户是在确认范围,即核实范围。

PMP参考答案:D.核实范围

PMP考试试题二:

You are managing a six-month project and have held bi-weekly meetings with your project stakeholders. After five-and-a-half months of work, the project is on schedule and budget, but the stakeholders are not satisfied with the deliverables. Thissituation will delay the project completion by one month. The MOST important process that could have prevented this situation is:

A. Monitor and Control Risks.

B. Control Schedule.

C. Define Scope.

D. Control Scope.

你正在管理一个历时六个月的项目,而且每两周要和项目干系人召开状态会议。工作完成五个半月后,项目的进度和预算均在计划内,但干系人对可交付成果并不满意。这样会导致项目延期一个月完工。阻止此类问题发生的最有效的过程是哪个?

A.控制风险

B.控制进度

C.定义范围

D.控制范围

PMP参考答案:C.定义范围

阅读本文的人还阅读了:
PMP考试费是多少?
2018年PMP考试费用多少?
2018年PMP考试时间?
2018年PMP考试时间安排
PMBOK第六版下载地址
PMP培训是什么?
PMP培训证明是什么?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库