PMP考试每天一练--PMP考试试题196
PMP考试试题一: A project manager begins a new project and wants to learn about a similar project’s successes and failures. However, only the closing documents were archived.What project document should the project manager reference to deliver the new project? A.work breakdown structure B.probability impact matrix C.project charter D.lessons learned 项目经理开始一个新项目,并希望了解类似项目的成功和失败。但是,只有存档收尾文档。项目经理应参阅哪一封项目文件来交付新项目? A.工作分解结构 B.可能性影响矩阵 C.项目章程 D.经验教训 PMP答案解析:了解类似项目的成功和失败,是经验教训总结。 PMP参考答案:D.经验教训 PMP考试试题二: You are evaluating vendor proposals and using selection criteria in order to choose a vendor. One of the criteria states that resources are required to have civil engineering degrees and a minimum of three years of experience. Which of the following tools and techniques does this question refer to: A. Weighting systems B. Procurement negotiation C. Independent estimate D. Screening systems 你在选择某种评估标准来评估供应商建议书,其中有一条标准是要求供应商的资源要有民用建筑工程学位,以及至少三年以上经验。这一评估技术是: A. 加权系统 B. 采购谈判 C. 独立估算 D. 筛选系统 PMP参考答案:D. 筛选系统 |