PMP考试每天一练--PMP考试试题195
PMP考试试题一: Which of the following typically occurs during the project’s closing phase? A.Measure customer satisfaction, draft the final project report, and apply final project scope changes. B.Obtain administrative closure, transfer team resources, balance the project budget., and archive project documentation C.Create the lessons learned report, update key stakeholders, and ensure that project deliverables conform to established quality standards D.Administer the acceptance process, capture lessons learned, prepare the final project report, and transfer team members 在项目收尾阶段通常会发生下列哪一项? A.测量客户满意度、起草最终项目报告并应用最终项目范围变更 B.获得行政收尾、转让团队资源、平衡项目预算并将项目文档存档 C.创建经验教训报告、更新关键干系人并确保项目可交付成果符合制定的质量标准 D.管理验收过程、收集经验教训、准备最终项目报告并转移团队成员 PMP答案解析:项目收尾步骤。见PMBOK 101页。 PMP参考答案:D PMP考试试题二: During project executing a project team member informs the project manager that based on her observations, the project cannot meet the quality standards set for it. The project manager meets with all parties concerned to analyze the situation. Which part of the quality management process is the project manager involved in: A. Perform Quality Assurance B. Quality analysis C. Quality Control D. Plan Quality Management 项目执行过程中,一团队成员告诉项目经理,根据她的研究,项目不能满足所设定的质量标准。于是项目经理和相关各方开会分析当前情况。项目经理正处于质量管理的哪个过程: A.实施质量保证 B.质量分析 C.控制质量 D.规划质量管理 PMP参考答案:A.实施质量保证 |