PMP考试每天一练--PMP考试试题190
PMP考试试题一: The project manager invites stakeholders to a project status review. The communication management plan includes 12 members.There are requests to include for 2 members. How many additional communication channels are required? A. 6 B. 27 C. 66 D. 120 项目经理邀请干系人参加项目状态评审。沟通管理计划中包含12名成员。同时额外请求增加2名干系人。那么还需要多少个额外沟通渠道? A. 6个 B. 27个 C. 66个 D. 120个 PMP答案解析:规划沟通管理工具-沟通需求分析( 10.1.2.1 )P292 PMP参考答案:B. 27个 PMP考试试题二: A project manager has run into cost difficulties. the project scope must be completed, but at less cost. the project manager should: A. Change the depreciation method for the equipment used on the project. B. Perform a value analysis. C. Evaluate benefit cost ratios. D. Recover some sunk costs. 项目经理的成本出现了问题,但项目范围还必须完成。在缺乏成本的情况下,项目经理应该: A. 更改项目对设备折旧的方法 B. 进行价值分析 C. 评估收益成本比率 D. 恢复部分沉淀成本 审题:此题目在关键句为“缺乏成本”“范围必须完成” 定位:项目成本管理 PMP参考答案:C. 评估收益成本比率 |