PMP考试试题一:

The project manager invites stakeholders to a project status review. The communication management plan includes 12 members.There are requests to include for 2 members. How many additional communication channels are required?

A. 6

B. 27

C. 66

D. 120

项目经理邀请干系人参加项目状态评审。沟通管理计划中包含12名成员。同时额外请求增加2名干系人。那么还需要多少个额外沟通渠道?

A. 6个

B. 27个

C. 66个

D. 120个

PMP答案解析:规划沟通管理工具-沟通需求分析( 10.1.2.1 )P292

PMP参考答案:B. 27个

PMP考试试题二:

A project manager has run into cost difficulties. the project scope must be completed, but at less cost. the project manager should:

A. Change the depreciation method for the equipment used on the project.

B. Perform a value analysis.

C. Evaluate benefit cost ratios.

D. Recover some sunk costs.

项目经理的成本出现了问题,但项目范围还必须完成。在缺乏成本的情况下,项目经理应该:

A. 更改项目对设备折旧的方法

B. 进行价值分析

C. 评估收益成本比率

D. 恢复部分沉淀成本

审题:此题目在关键句为“缺乏成本”“范围必须完成”

定位:项目成本管理

PMP参考答案:C. 评估收益成本比率

阅读本文的人还阅读了:
PMBOK第六版下载地址
北京PMP考试地点
上海PMP考试地点
深圳PMP考试地点
PMP退考费多少?
PMP认证抽审流程是什么?
PMP考试是什么?

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库