PMP考试每天一练--PMP考试试题188
PMP考试试题一: A project is ahead of schedule, which the budget is overrun. Which of the following could be the schedule and cost performance indices? A. schedule performance index is 1.20 and the cost performance index is 1.15 B. schedule performance index is 1.10 and the cost performance index is 0.09 C. schedule performance index is0.95 and the cost performance index is 0.85 D. schedule performance index is 0.90 and the cost performance index is 1.10 某项目进度超前,但是预算超支,下列哪一项可能是项目进度和成本绩效指数? A. 进度绩效指数为1.20;成本绩效指数为1.15 B. 进度绩效指数为1.10;成本绩效指数为0.09 C. 进度绩效指数为0.95;成本绩效指数为0.85 D. 进度绩效指数为0.90;成本绩效指数为1.10 PMP答案解析:挣值管理(7.4.2.1)P217 PMP参考答案:B. 进度绩效指数为1.10;成本绩效指数为0.09 PMP考试试题二: Lack of communication and unsolved arguments imply: A. Complicated project. B. Crashed schedule. C. Inefficient project team. D. Undefined responsibility of project team. 缺少沟通和争议未解决意味着: A. 项目错综复杂 B. 进度计划失灵 C. 项目小组效率不高 D. 项目小组职责不明确 审题:此题涉及沟通和争议,属于人力资源管理内容。 定位:人力资源管理的拓展。 PMP参考答案:C. 项目小组效率不高 |