PMP考试试题一:

A project is ahead of schedule, which the budget is overrun. Which of the following could be the schedule and cost performance indices?

A. schedule performance index is 1.20 and the cost performance index is 1.15

B. schedule performance index is 1.10 and the cost performance index is 0.09

C. schedule performance index is0.95 and the cost performance index is 0.85

D. schedule performance index is 0.90 and the cost performance index is 1.10

某项目进度超前,但是预算超支,下列哪一项可能是项目进度和成本绩效指数?

A. 进度绩效指数为1.20;成本绩效指数为1.15

B. 进度绩效指数为1.10;成本绩效指数为0.09

C. 进度绩效指数为0.95;成本绩效指数为0.85

D. 进度绩效指数为0.90;成本绩效指数为1.10

PMP答案解析:挣值管理(7.4.2.1)P217

PMP参考答案:B. 进度绩效指数为1.10;成本绩效指数为0.09

PMP考试试题二:

Lack of communication and unsolved arguments imply:

A. Complicated project.

B. Crashed schedule.

C. Inefficient project team.

D. Undefined responsibility of project team.

缺少沟通和争议未解决意味着:

A. 项目错综复杂

B. 进度计划失灵

C. 项目小组效率不高

D. 项目小组职责不明确

审题:此题涉及沟通和争议,属于人力资源管理内容。

定位:人力资源管理的拓展。

PMP参考答案:C. 项目小组效率不高

阅读本文的人还阅读了:
2018年PMP考试时间?
2018年PMP考试时间安排
关于PMP考试费价格调整的通知
PMBOK第六版下载地址
北京PMP考试地点
如何参加PMP考试?
PMP项目管理考试费用变更
PMP考试题库

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库