PMP考试每天一练--PMP考试试题187
PMP考试试题一: A large change order is approved which will impact the project baseline. What should the project manager do once this change is approved? A. Re-baseline the project and notify the team B. Inform the financial department about the change in budget C. Ask for a steering committee meeting D. Schedule a project team meeting to discuss options 一个获得批准的大变更单将会影响到项目基准,一旦变更获得批准,项目经理应该怎么做? A. 重订项目基准并通知团队 B. 通知财务部门预算变更 C. 要求召开指导委员会会议 D. 安排一次项目团队会议,讨论各种方案 PMP答案解析:整体变更控制流程(4.5)P94 PMP参考答案:A. 重订项目基准并通知团队 PMP考试试题二: The internal rate of return is a measure of a project's expected profitability that can be thought of as the- A. After-tax profit reported to the government. B. Maximum rate of interest that may be paid for the capital used over the life of the investment without loss on the project. C. EAC minus BAC. D. Ratio of discounted revenues over discounted costs. 内部回报率是项目预期利益率的评定标准,可以把它看作: A. 向政府汇报的税后利润 B. 在投资生命期利用的没有项目损失的资金应该支付的最大利率 C. 完工估算(EAC)减完工预算(BAC) D. 贴现收入和贴现成本的比率 审题:内部回报率IRR是一种投资项目评估的方法。很明显是成本相关的 定位:成本管理的拓展 解析:IRR就是收益为零时,资金的最大利率 PMP参考答案:B |