PMP考试每天一练--PMP考试试题186
PMP考试试题一: A project manager is pleased the company has obtained a project in a new geographic location. The project manager identifies and prioritizes the risks of this project.Which of the following actions should the project manager take next? A. Initiate the risk process B. Identify threats and opportunities C. Plan to enhance opportunities and reduce threats D. Review and update risk information 项目经理很高兴公司在新地区取得项目。项目经理识别了该项目风险并予以排序。项目经理接下来应采取下列哪项行动? A. 启动风险过程 B. 识别威胁和机遇 C. 计划促进机会并降低威胁 D. 审查并更新风险信息 PMP答案解析:过程组间的逻辑顺序 PMP参考答案:C. 计划促进机会并降低威胁 PMP考试试题二: Your boss believes that all of your project team members avoid work as much as possible. He or she often uses threats and various control schemes to make sure people are doing their jobs. Which approach to managing people does your boss follow? A. Maslow's hierarchy of needs. B. Theory X. C. Theory Y. D. Herzberg's motivation and hygiene factors. 你的老板认为你的所有团队成员都在尽可能少工作,他用了很多威胁和其他监督手段来让大家完成工作,他的管理方法说明了: A. 马斯洛的需求层次论 B. X理论 C. Y理论 D. 赫兹伯格的激励和保健理论 审题: 此题关键句“尽可能少工作” “威胁和其他监督” 定位:人力资源管理的拓展。 PMP参考答案:B. X理论 |