以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练--PMP考试试题186

转载者:PMP团购网      发布时间:2017/12/13        点击: 2563

PMP考试试题一:

A project manager is pleased the company has obtained a project in a new geographic location. The project manager identifies and prioritizes the risks of this project.Which of the following actions should the project manager take next?

A. Initiate the risk process

B. Identify threats and opportunities

C. Plan to enhance opportunities and reduce threats

D. Review and update risk information

项目经理很高兴公司在新地区取得项目。项目经理识别了该项目风险并予以排序。项目经理接下来应采取下列哪项行动?

A. 启动风险过程

B. 识别威胁和机遇

C. 计划促进机会并降低威胁

D. 审查并更新风险信息

PMP答案解析:过程组间的逻辑顺序

PMP参考答案:C. 计划促进机会并降低威胁

PMP考试试题二:

Your boss believes that all of your project team members avoid work as much as possible. He or she often uses threats and various control schemes to make sure people are doing their jobs. Which approach to managing people does your boss follow?

A. Maslow's hierarchy of needs.

B. Theory X.

C. Theory Y.

D. Herzberg's motivation and hygiene factors.

你的老板认为你的所有团队成员都在尽可能少工作,他用了很多威胁和其他监督手段来让大家完成工作,他的管理方法说明了:

A. 马斯洛的需求层次论

B. X理论

C. Y理论

D. 赫兹伯格的激励和保健理论

审题: 此题关键句“尽可能少工作” “威胁和其他监督”

定位:人力资源管理的拓展。

PMP参考答案:B. X理论

阅读本文的人还阅读了:
PMBOK第六版下载地址
北京PMP考试地点
上海PMP考试地点
深圳PMP考试地点
PMP一般的学习流程简介
PMP项目管理考试费用变更
PMP试题权重比例及评分规则
PMP审查常见问题

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库