PMP考试每天一练--PMP考试试题185
PMP考试试题一: A project manager has been collecting work performance information during the project execution phase. What is the main purpose of this action? A. To monitor cost, schedule progress, and deliverable status. B. To monitor team member performance in the project C. To assess training requirements within the project team D. To update the project management plan 项目经理在项目执行阶段已经收集了工作绩效信息。此项活动的主要目的是什么? A. 监测成本,进度,和可交付状态 B. 监测小组成员执行的项目进程 C. 评估项目团队的培训需求 D. 更新项目管理计划 PMP答案解析:监控项目工作输入-工作绩效信息 ( 4.4.1.5 )P90 PMP参考答案:A. 监测成本,进度,和可交付状态 PMP考试试题二: The need for ( ) is one of the major driving forces for communication in a project: A. Optimization. B. Integrity. C. Integration. D. Differentiation. _________的需求是项目沟通的一个巨大驱动力。 A. 最优化 B. 完整 C. 整合 D. 区别 审题:题干提到项目沟通,很明显是沟通管理相关的题目。 定位:沟通管理的拓展 解析:项目沟通管理就是为了满足整合管理中的复杂多样的沟通需求。 PMP参考答案:C. 整合 |