PMP考试每天一练--PMP考试试题184
PMP考试试题一: Because you are working under a firm-fixed-price contract,management wants you to submit the final invoice and close out the contract as soon as possible. Before final payment on the contract can be authorized, you must A. Prepare a contract completion statement B. Audit the procurement process C. Update and archive contract records D. Settle subcontracts 你正在依据一个固定价格合同工作,管理层要求你提交一份最终发票,尽快结束合同。在根据合同最终付款得到批准之前,你必须 A. 准备一份合同完成陈述 B. 对采购流程进行审计 C. 更新和整理合同记录 D. 处理分包合同 PMP答案解析:结束采购引言(12.4)P387 PMP参考答案:D. 处理分包合同 PMP考试试题二: If project A has an NPV of $30,000 and project B of $50,000, what is the opportunity cost if project B is selected? A. $23,000. B. $30,000. C. $20,000. D. $50,000. 如果项目 A 的净现值为 30000 美元,项目 B 的为 50000 美元,那么选取项目 B 的机会成本是多少? A. $23,000 B. $30,000 C. $20,000 D. $50,000 审题:此题关键句“机会成本” “选取项目 B” 定位:成本管理的扩展 解析:机会成本(Opportunity Cost):是指为了得到某种东西而所要放弃另一些东西的最大价值。 净现值(Net Present Value)是一项投资所产生的未来现金流的折现值与项目投资成本之间的差值。选项目B则放弃项目A PMP参考答案:B. $30,000 |