以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练--PMP考试试题-47

转载者:PMP团购网      发布时间:2017/1/10        点击: 2761

PMP考试试题一:

Who controls the indirect (overhead) costs of a project?

A. Project manager

B. Executive management

C. Cost accounts manager

D. Internal auditor

是谁控制一个项目的间接成本(管理费)?

A. 项目经理

B. 高级管理层

C. 成本帐目经理

D. 内部审计员

PMP参考答案:B. 高级管理层

PMP答案解析:成本分类-间接成本

PMP考试试题二:

During the Define Activities process, a team member begins to discuss activities that the project manager has never heard discussed. What should the project manager do?

A. Make sure he has a good understanding of the activities and include the activities in the activity list.

B. Ask the team member to explain why such an activity would be needed to complete the work package.

C. Make sure the entire team agrees that the activities should be done.

D. Evaluate the impact of the change.

在定义活动过程中,一团队成员开始讨论一个项目经理从来没有听过的活动。此时项目经理应该怎么做?

A.确保团队成员理解并将这些活动包含在活动清单里了。

B.询问团队成员需要完成这些活动的原因。

C.确认所有团队成员都认同这些活动。

D.评估变更的影响。

审题: 此题的关键字为“定义活动”“讨论”,项目进入规划阶段的范围管理中的定义活动过程

定位: 规划过程组·时间管理·6.2 定义活动

解析:

1、定义活动过程的目的是对活动(为完成工作包而必须开展的工作)进行定义,项目经理需要确认该活动是必须开展的;因此本题答案为B;

2、选项A活动清单是定义活动过程的输出,排除;选项C是WBS的作用,排除;选项D为监控过程组的工作,排除;

3、此题的场景是干扰项,对选择没有作用,解题需要了解定义活动的目的和活动的定义。

答案:B.询问团队成员需要完成这些活动的原因。

阅读本文的人还阅读了:
PMP考试有题库吗?
PMBOK十大知识领域是什么?
PMP培训机构是什么?
PMP认证流程是怎样的?
怎么看PMP考试成绩?
PMP考试报名费是多少?
PMP对企业有什么好处?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库