PMP考试每天一练--PMP考试试题-45

转载者:PMP团购网      发布时间:2017/1/4        点击: 3558

PMP考试试题一:

At a project’s completion, the customer refuses to pay a portion of the totalamount based on a subjective determination of the vendor’s performance. Thecontract would be which of the following?

A. Cost-plus-award-fee

B. Firm-fixed-price

C. Cost-plus-incentive-fee

D. Fixed-price-incentive-fee

项目完成时,客户根据对应供应商绩效的主观决定,拒绝支付其中一部分总金额,合同应属于下列哪一项?

A.成本加奖励费用合同

B.固定总价合同

C.成本加激励费用合同

D.固定总价加激励费用合同

PMP参考答案:A.成本加奖励费用合同

PMP答案解析:规划采购输入:合同类型(12.1.1.9) P362

PMP考试试题二:

A supplier is selected for a statement of work, due to previous experience withsimilar project. During the project’s execution, the supplier announces that they cannot fulfill their responsibilities. To ensure a formal evaluation review in the selection of a supplier, what should the project manager have done?

A. Defined and utilized weighted criteria

B. Organized bidder conferences

C. Prepared an independent estimate

D. Utilized the Delphi technique

由于之前类似项目的经验,一名供应商被选择来执行工作说明书。在项目执行期间,供应商宣布他们无法履行其责任。为了确保在选择供应商时进行正式评估审查,项目经理应完成哪一项工作?

A. 定义并利用加权标准

B. 组织投标人会议

C. 准备独立估算

D. 利用德尔菲技术

PMP参考答案:A. 定义并利用加权标准

PMP答案解析:实施采购工具-建议书评价技术(12.2.2.2 ) P375

阅读本文的人还阅读了:
PMP认证费用多少?
PMP考试有题库吗?
PMBOK十大知识领域是什么?
PMP培训机构是什么?
PMP认证流程是怎样的?
怎么看PMP考试成绩?
PMP考试报名费是多少?
PMP对企业有什么好处?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库