PMP考试每天一练--PMP考试试题-43

转载者:PMP团购网      发布时间:2016/12/29        点击: 2547

PMP考试试题一:

Effective communication is vital for project success. Scope changes,constraints, assumptions, integration and interface requirements, overlapping roles and responsibilities, and many other factors all pose communications challenges.The presence of communication barriers is most likely to lead to。

A. Reduced productivity

B. Increased hostility

C. Low morale

D. Increased conflict

有效的沟通对于项目的成功至关重要。范围变更、限制条件、假设、整合与界面要求,重叠的角色和责任以及其它许多因素都对沟通提出了挑战。沟通上的障碍很可能导致:

A. 生产力下降

B. 敌意增强

C. 士气低落

D. 冲突增加

PMP参考答案:D. 冲突增加

PMP答案解析:规划沟通管理引言(10.1) P289

PMP考试试题二:

During the Plan Risk Management process of a major project, the project manager is informed that her key subject matter experts are currently spread around the globe. All experts are available via e-mail and planning must not be delayed. What is the BEST method for gathering information?

A. Brainstorming.

B. Delphi technique.

C. Assumption analysis.

D. Cause and effect diagramming.

某一重大项目处于规划风险管理阶段。项目经理被告知,项目的关键问题专家现在都派往全世界各地了,他们只能通过邮件方式给出建议,而且计划不能延误。收集信息的最佳方法是什么?

A.头脑风暴。

B.德尔菲技术。

C.假设分析。

D.因果图。

审题: 此题的关键字为“规划风险管理阶段”和“收集信息”和“项目的关键问题专家现在都派往全世界各地了,他们只能通过邮件方式给出建议”,意思就是项目处于风险管理中的规划过程组,考查的是工具中的信息收集的技术。

定位: 规划过程组·风险管理·11.2.2 识别风险:工具与技术

解析: 此题可以使用头脑风暴、面谈和德尔菲技术。但由于专家们都分散在全球各地,所以使用头脑风暴和面谈法不切合实际。

答案:B.德尔菲技术。

阅读本文的人还阅读了:
PMP考试有题库吗?
PMBOK十大知识领域是什么?
PMP培训机构是什么?
PMP认证流程是怎样的?
怎么看PMP考试成绩?
PMP考试报名费是多少?
PMP对企业有什么好处?
PMP考点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库