PMP考试每天一练--2016年PMP考试模考试题-9
PMP英文试题:9. A company’s management team wants to hire a resource to manage a software update to the company’s existing product; the product is one of several in a department that has other important activities. Which of the following candidates should be selected to manage the software update? A. Experienced software developer B. External consultant C. Department manager D. Part-time project manager PMP中文翻译:9.一家公司的管理团队希望雇佣一名资源,来管理对公司现有产品的软件升级。该产品是某个部门多个产品的其中一个产品,且该部门还有其它重要活动.那么应该选择下列哪一个候选人来管理软件更新? A. 经验丰富的软件开发人员 B. 外部顾问 C. 部门经理 D. 兼职项目经理 PMP参考答案:D 兼职项目经理 PMP答案解析:项目的特点 ( 1.2) |