PMP考试每天一练--2016年PMP考试试题及答案解析7
7、A project manager has just been assigned to a new project and has been given the project charter.The FIRST thing the project manager must do is: A.create a project scope statement. B.confirm that all the stakeholders have had input into the scope. C.analyze project risk. D.begin work on a project management plan. 7、项目经理刚刚分配到新项目上,已经完成项目章程。项目经理首先应该做什么? A、创建项目范围说明书 B、确保所有的干系人有输入到范围中 C、分析项目风险 D、开始项目管理计划上的工作 正确答案:B 试题解答:选项B等于识别干系人。 |