PMP考试章节练习--合同与采购管理11-15

转载者:PMP团购网      发布时间:2014/11/22        点击: 3335

合同与采购管理-PMP考试章节练习(11-15题)

11. The Cost Plus Incentive Fee (CPIF) contract provides:
A. reimbursement of allowable costs plus a fixed fee which may be paid proportionately as the contract progresses
B. the supplier for the cost of delivered performance plus a predetermined fee for superior performance
C. incentive to the seller for reducing performance costs so as to increase profits
D. B andC

成本加奖励费用合同提供:
A. 允许成本的补偿加上一个固定的费用,后者是随着合同的进度按比例支付
B. 供货方的履约成本加上预先规定的突出表现费
C. 刺激卖方降低执行成本以增加利润
D. B 和C

12. Fixed Price Plus Incentive Fee (FPPIF) contracts provide for:
A. reimbursement of allowable costs plus a fixed fee which may be paid proportionately as the contract progresses
B. reimbursement of allowable cost of services performed plus an agreed upon fixed fee which is usually a percentage of the estimated cost, as profit
C. the supplier with a fixed price for delivered performance plus a predetermined percentage fee for superior performance
D. the supplier and owner sharing of a predetermined fee, based upon how much project costs are controlled

固定价格加奖励费用提供了:
A. 报销允许的成本加上一个固定的费用,后者是随着合同的进度按比例支付
B. 报销允许的服务费用加上一个已经同意的估算费用的百分比作为利润
C. 以固定价格供支付货方的履约成本,加上预先确定的百分比做为突出表现费
D. 供货方和业主根据所控制的项目成本共同承担预先确定的费用

13. A Firm Fixed Price (FFP) Contract mandates the contractor to
A. provides a set of goods and services at a fixed price
B. provide a set of goods and services at a variable price
C. provide goods/services at unit rates with the final price being dependent on the quantities needed to carry out the work
D. provide services based upon the amount of time and supplies used

完全固定价格合同要求承包商
A. 以固定价格提供一套商品和服务
B. 以可变价格提供一套商品和服务
C. 以单位价格提供商品/服务,合同的最终价格由执行工作所需的(商品/服务)数量而定
D. 以项目中消耗的时间和供应品的数量提供服务

14. Comprehensive project specifications are important so that:
A. both the buyer and seller are working from same baseline
B. the buyer can spend as little money as possible up front
C. the seller reduces risk in a Fixed Price contract situation
D. A andC

陈述全面的项目说明书很重要,以便:
A. 买卖双方的工作应该基于相同基点
B. 买方可以预先尽可能少花钱
C. 卖方可以降低固定价格合同中的风险
D. A 和C

15. The major type(s) of standard warranty (ies) that are used in the business environment is(are)
A. Express
B. Implied
C. Negotiated
D. A andB

在商业环境中使用的标准保证条款的主要类型是:
A. 明示的
B. 暗指的
C. 协商的
D. A 和B

PMP考试练习答案(合同采购):11-15 DCADD

阅读本文的人还阅读了:
为什么很多公司优先录用PMP?
PMP证书的含金量?
PMP认证考试需要准备什么?
PMP考试内容是什么?
为什么要参加PMP培训?

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库