PMP考试题库之项目成本管理6-10题:6. Cost Variance (CV) is which of the following equations?
A. CV= BCWP – BCWS
B. CV= BCWP –ACWP
C. CV= SV/BCWS
D. A andC
成本偏差(CV)是下面的哪个公式?
A. CV= BCWP – BCWS
B. CV= BCWP –ACWP
C. CV= SV/BCWS
D. A andC
7. In the following table, which project is most likely to finish ahead of schedule? Project BCWS BCWP ACWP
A 1000 800 600
B 1000 600 800
C 1000 1200 800
A. Project A
B. Project B
C. Project C
D. All three the projects will be completed at the same time
下面的表中,哪个项目最可能会提前完成?
A. 项目A
B. 项目B
C. 项目C
D. 所有三个项目会在同时完成
8. Based on the information in question 7, which will most likely be completed within time and
cost constraints?
A. Project A
B. Project B
C. Project C
D. Both A and B answers
在第七题的基础下,哪个项目会在时间要求以及成本要求内完成?
A. 项目A
B. 项目B
C. 项目C
D. A 和B
9. Cost budgeting can be best described by which of the following?
A. The process of developing the future trends along with the assessment of probabilities, uncertainties, and inflation that could occur during the project
B. The process of assembling and predicting costs of a project over its life cycle
C. The process of establishing budgets, standards, and a monitoring system by which the investment cost of the project can be measured and managed
D. The process of gathering, accumulating, analyzing, monitoring, reporting, an d managing the costs on an on-going basis.
下面哪个是对成本预算最合适的描述?
A. 制定未来发展趋势以及评估项目中可能发生的概率、不确定性以及通货膨胀的过程
B. 对项目在命周期中的成本进行计算和预测的过程
C. 建立预算、标准和检测系统以进行对项目投资的衡量和管理的过程
D. 在项目进行过程中收集、累计、分析、检测、报告和管理成本的过程
10. Which of the following is a direct project cost?
A. Lighting and heating for the corporate office
B. Workers Compensation insurance
C. Piping for an irrigation project
D. A andB
下面哪一项是项目直接成本?
A. 公司办公室的照明和取暖费用
B. 职员的赔偿保险
C. 为一个灌溉项目装管道
D. A 和B
PMP认证考试题参考答案:6-10 BCCCC