PMP考试每天一练-2023年PMP考试模拟题83
PMP考试练习题一: 项目 A 已经交付给客户 A ,而且开始开展收尾活动。项目团队将会转到客户B的项目上工作。销售经理要求项目经理提供项目A的售后支持。项目经理应执行下列哪一项? Project A is delivered to customer A and the closure activities are carried out. The project team will be transferred to work on project B for customer B. The sales manager requests the project manager provide post-sales support for project A. Which of the following should the project manager do? A:将项目团队转移到项目B上,开始新的启动活动. Move the project team to project B and start new initiation activities. B:建议销售经理获得新的资源 Suggest the sales manager obtain new resources. C:确保项目A的特定知识已获收集,并移交组织 Ensure project A’s specific knowledge is captured and transferred to the organization D:拒绝销售经理的请求,并查阅合同 Deny the sales manager’s request and refer to the contract PMP考试答案解析:指南-4.7结束项目或阶段,项目或阶段行政收尾所需的必要活动包括管理知识分享和传递。 PMP考试参考答案:C PMP考试练习题二: 以下关于质量测量指标的说法,哪一个是正确的? A. 质量测量指标应该定得略高一些,以便使工作具有挑战性。 B. 质量测量指标通常以质量核对表的形式出现。 C. 质量测量指标不需要非常具体,以便有一定的灵活性。 D. 质量测量指标是对质量标准的非常具体的操作性定义,用于管理质量和控制质量中。 PMP考试参考答案:D |