PMP考试每天一练-2023年PMP考试模拟题58
PMP考试练习题一: 项目团队正在讨论。幸运的是项目经理已经建立了奖励机制和团队建设,有助于鼓励团队进一步合作。团队最近讨论的一件事是他们是否应自己完成一工作包还是外包给其他人。他们现在肯定是在采购过程的哪个阶段? The project team seems to like to argue; they have argued about everything. Luckily the project manager has set in place a reward system and team building sessions that will help and encourage the team to cooperate more. The latest thing they are arguing about is if they should complete a work package themselves or outsource the work to someone else. What part of the procurement process must they be in? A、控制采购 Control Procurements B、规划采购管理 Plan Procurement management C、实施采购 Conduct Procurements D、结束采购 Close Procurements PMP考试答案解析:12.1.3.6 自制或外购决策通过自制或外购分析,做出某项特定工作最好由项目团队自己完成,还是需要从外部渠道采 购的决策。 PMP考试参考答案:B PMP考试练习题二: 如果挣值是 300,000 美元,实际成本是 355,000 美元,计划价值是 370,000 美元,项目的进度绩效指数是: A、 85% B、 125% C、116% D、81% PMP考试参考答案:D |