PMP考试每天一练-2023年PMP考试模拟题56

转载者:PMP团购网      发布时间:2023/5/3        点击: 478

PMP考试练习题一:

一家公司将更换使用了10年、不再符合市场需求基于旧平台的集成系统。在项目规划期间,管理人员将一个更灵活的价格结构作为关键需求。高级管理人员还未决定如何满足这项需求,但是同意该需求的战略正确性。在项目执行期间,价格结构的变更将要求频繁的返工和重新测试。下列哪项项目计划元素能够系统的解决这些问题?

A company will be replacing its integrated systems after 10 years of service from a legacy platform that on longer meets market needs. During project planning, managers identify a more flexible pricing structure as a key requirement. Senior managers have not yet decided how to meet this requirement but agree it is strategically correct. During project execution, changes in the pricing structure will require frequent rework and retesting. Which of the following is an element of the project plan that addresses this in a systemic way?

A:项目变更需要获得高级管理人员批准的质量政策

A quality policy requiring project changes to be approved by senior managers

B:能够从新需求中识别风险的风险应对计划

A risk response plan that would identify risks from new requirements

C:实施价格结构变更的人员增加计划

A staff augmentation plan to implement pricing structure changes

D:具有详细实施需求的范围说明书

A scope statement with detailed requirements for implementation

PMP考试答案解析:指南-5.3.3.1项目范围说明书,明确产品验收标准,明确可交付成果等,代表了项目相关方之间就项目范围所达成的共识,并为评价变更请求提供基准。

PMP考试参考答案:D

PMP考试练习题二:

通过评审累计成本曲线,项目经理可以监控____。

A.挣值

B.计划价值

C.成本偏差

D.成本绩效指数

PMP考试参考答案:D

阅读本文的人还阅读了:
PMP考试报名费是多少?
PMP考试时间安排
pmp是什么简称?
项目管理师pmp报考条件?
PMP培训机构是什么?
PMP哪个培训机构好?
PMP不参加培训能考试吗?
PMP培训是什么?
pmp可以自己报考吗?
pmp是英文考试吗?
2023年PMP考试时间

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库