PMP考试每天一练-2023年PMP考试模拟题56
PMP考试练习题一: 一家公司将更换使用了10年、不再符合市场需求基于旧平台的集成系统。在项目规划期间,管理人员将一个更灵活的价格结构作为关键需求。高级管理人员还未决定如何满足这项需求,但是同意该需求的战略正确性。在项目执行期间,价格结构的变更将要求频繁的返工和重新测试。下列哪项项目计划元素能够系统的解决这些问题? A company will be replacing its integrated systems after 10 years of service from a legacy platform that on longer meets market needs. During project planning, managers identify a more flexible pricing structure as a key requirement. Senior managers have not yet decided how to meet this requirement but agree it is strategically correct. During project execution, changes in the pricing structure will require frequent rework and retesting. Which of the following is an element of the project plan that addresses this in a systemic way? A:项目变更需要获得高级管理人员批准的质量政策 A quality policy requiring project changes to be approved by senior managers B:能够从新需求中识别风险的风险应对计划 A risk response plan that would identify risks from new requirements C:实施价格结构变更的人员增加计划 A staff augmentation plan to implement pricing structure changes D:具有详细实施需求的范围说明书 A scope statement with detailed requirements for implementation PMP考试答案解析:指南-5.3.3.1项目范围说明书,明确产品验收标准,明确可交付成果等,代表了项目相关方之间就项目范围所达成的共识,并为评价变更请求提供基准。 PMP考试参考答案:D PMP考试练习题二: 通过评审累计成本曲线,项目经理可以监控____。 A.挣值 B.计划价值 C.成本偏差 D.成本绩效指数 PMP考试参考答案:D |