PMP考试练习题一:

在大型项目中,可在不同层次制订责任分配矩阵(RAM)。下列那个选项体现了 RAM 的层次?

On larger projects, a Responsibility Assignment Matrix(RAM)can be developed at various levels. Which option exemplifies the RAM’s levels?

A:高层次可定义项目团队中的各小组分别负责 WBS 中的哪部分工作,而低层次则可在各小组内为具体活动分配角色、职责和职权。

High-level can define a project team group or unit is responsible for within each component of the WBS, while lower-level are used within the group to designate roles, responsibilities, and levels of authority for specific activities.

B:低层次仅可以用来指定特定活动的职权级别

Lower level is used only to designate levels of authority for specific activities.

C:所有层次都可以用来指定角色,职责以及特定活动的职权级别

All levels are used to designate roles, responsibilities, and levels of authority for specific activities.

D:高层次允许个人查看与其有关的所有活动

High level allows a person to see all activities associated with one person.

PMP考试答案解析:9.1.2。可以采用责任分配矩阵(RAM)显示工作包或活动与项目团队成员之间的联系。在大型项目中,可在多个层次上制定 RAM。例如,高层次的 RAM 可定义项目团队中的各小组分别负责WBS 中的哪部分工作,而低层次的 RAM 则可在各小组内为具体活动分配角色、职责和职权。矩阵图能反映与每个人相关的所有活动以及与每项活动相关的所有人员。它也可确保任何一项任务都只有一个人负责,从而避免混乱。

PMP考试参考答案:A

PMP考试练习题二:

某项目绩效信息如下:EV=10,000,AC=12,000,PV=9,000,BAC=50,000.请问 1,完成的百分比 2,如果绩效维持原状到结束,EAC=?

A.16.7%;60000

B.20%; 60000

C.16.7%;52000

D.20%; 52000

PMP考试参考答案:B

阅读本文的人还阅读了:
pmbok第七版+第六版英文版 pdf
PMP考试认证费是多少?
pmp考试时间几点到几点?
pmp英文全称是什么?
考pmp证有什么要求?
PMP培训是什么?
pmp中文全称是什么?
pmp考试时间是哪天?
PMP考试费用及缴费方式是什么?
pmp教材第七版+第六版pdf下载

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库