PMP考试每天一练-2023年PMP考试模拟题51
PMP考试练习题一: 项目经理被任命管理一个为期多年的项目。在创建工作分解结构(WBS)过程中,项目团队无法分解将在项目后期发生的某些阶段。项目经理应该怎么做? A project manager is assigned to a multiyear project. During creation of the work breakdown structure(WBS), the project team is unable to decompose some of the phases that will occur during later stages of the project. What should the project manager do? A:适当的时候,开展滚动式规划。 Conduct rolling wave planning when appropriate B:回到需求收集阶段 Return to the requirements gathering stage C:为这些阶段预估WBS分解 Estimate WBS decomposition for those phases D:减少项目范围 Reduce the project scope PMP考试答案解析:参见 6.2.2.3 。考点:滚动式规划。 PMP考试参考答案:A PMP考试练习题二: 由于项目发生主要的范围变更,你已批准的成本基准发生了变动。你下一步应当____。 A.估算范围变更的量级 B.发布预算的更新 C.书面记录经验教训 D.执行已批准的范围变更 PMP考试参考答案:B |