PMP考试每天一练-2023年PMP考试模拟题26
PMP考试练习题一: 由于一台设备设计规格中的某一项被忽略了而导致项目延期,而赶制此项需要更长的交货期。为避免这种情况的发生,项目经理在项目规划期间应完成下列哪一项? A project is delayed because one item in the equipment specification has been ignored. It will require a longer lead time to catch up. To avoid this situation, the project manager should have done which of the following in project planning? A:A 制定应急计划 prepare a contingency plan B:选择更为可靠的供应商 select a more reliable supplier C:在识别风险过程上花费更多的努力 spend more efforts on the process of risk identification D:确保该项不在关键路径上 ensure that the item is a not on the critical path PMP考试答案解析:所属过程组:规划过程组。所属知识领域:项目风险管理。出现这种情况识别风险不充分。 PMP考试参考答案:C PMP考试练习题二: 以下哪项不是用于进度控制的工具或技术? A.偏差分析 B.三点估算 C.假设情景分析 D.资源平衡 PMP考试参考答案:B |