PMP考试每天一练-2023年PMP考试模拟题12

转载者:PMP团购网      发布时间:2023/1/25        点击: 554

PMP考试练习题一:

你的管理层总是要削减你的项目估算的 10%。你的新的项目范围还不清楚,包含 30 多个项目相关方。管理层预计由于该项目将降低 25%的停机时间。这种情况下哪项是最好的解决办法?

You have always been asked by your management to cut your project estimate by ten percent after you have given it to them. The scope of your new project is unclear and there are over 30 stakeholders. Management expects a 25 percent reduction in downtime as a result of the project. Which of the following is the BEST course of action in this situation?

A:重新计划获得 35%的停机时间改进

Re-plan to achieve a 35 percent improvement in downtime.

B:减少估算,并在风险应对计划中注明变更

Reduce the estimates and note the changes in the risk response plan.

C:提供准确的实际成本估算并能支撑该结果

Provide an accurate estimate of the actual costs and be able to support it.

D:会见团队以确认从哪里可以找到 10%的节约

Meet with the team to identify where you can find lo percent savings.

PMP考试答案解析:7.2.2.8-决策,这是项目的一个常见问题,很多没有经验的项目经理用选项B或D处理。如果你的估算是准确的,你就有义务坚持(选项C)。管理层的唯一选择以削减成本是支持项目经理寻找与 三约束相关的解决方法。选项 A没有说明手头的问题,成本。

PMP考试参考答案:C

PMP考试练习题二:

定义活动过程所得到的最终成果是:

A 可交付成果

B 活动

C 工作包

D 工作任务

PMP考试参考答案:B

阅读本文的人还阅读了:
pmp考试时间是哪天?
pmp是什么认证?
长沙pmp培训机构排名
pmp报考条件必须参加培训吗?
什么是PMP培训机构?
PMP培训费和考试费是多少?
考pmp需要什么条件?
上海pmp培训机构哪个比较好?
pmp是什么考试?
PMP报名时间是哪天?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库