PMP考试每天一练-2022年PMP考试模拟题113
PMP考试练习题一: 项目目前处于执行的中间阶段。项目落后于进度,而且面临成本超支的问题。在这个时候,客户提出变更现有需求的请求。项目经理应该采取下列哪一项措施? A project is in the middle of execution. The project is running behind schedule and faces cost overruns. During this period, the customer requests a change to existing requirements. The project manager should do which of the following action? A:与团队成员讨论当前版本是否允许变更 Discuss with the team member whether or not the change can be accommodated in the current release. B:立即开始变更工作,节省时间和成本。 Start to immediately work on the change to save time and cost. C:确保变更已用文件记录,并遵循正式的变更流程。 Ensure that the change is documented and the formal change process is followed. D:分析成本和进度影响,并通知客户。 Analyze the cost and schedule impact and inform the customer. PMP考试答案解析:4.6实施整体变更控制-引言。“项目的任何人都可提出变更请求,可以口头,但必须书面记录,并纳入变更管理和配置管理系统中。” PMP考试参考答案:C PMP考试练习题二: 下列哪项不是整体变更控制的内容 A.对可能引起变更的因素施加影响 B.在整个项目期间和整个范围内协调各种类型的变更 C.确保项目的绩效测量基准不发生变化 D.当变更实际发生时对变更进行管理 PMP考试参考答案:C |