PMP考试每天一练-2022年PMP考试模拟题113

转载者:PMP团购网      发布时间:2022/9/28        点击: 640

PMP考试练习题一:

项目目前处于执行的中间阶段。项目落后于进度,而且面临成本超支的问题。在这个时候,客户提出变更现有需求的请求。项目经理应该采取下列哪一项措施?

A project is in the middle of execution. The project is running behind schedule and faces cost overruns. During this period, the customer requests a change to existing requirements. The project manager should do which of the following action?

A:与团队成员讨论当前版本是否允许变更

Discuss with the team member whether or not the change can be accommodated in the current release.

B:立即开始变更工作,节省时间和成本。

Start to immediately work on the change to save time and cost.

C:确保变更已用文件记录,并遵循正式的变更流程。

Ensure that the change is documented and the formal change process is followed.

D:分析成本和进度影响,并通知客户。

Analyze the cost and schedule impact and inform the customer.

PMP考试答案解析:4.6实施整体变更控制-引言。“项目的任何人都可提出变更请求,可以口头,但必须书面记录,并纳入变更管理和配置管理系统中。”

PMP考试参考答案:C

PMP考试练习题二:

下列哪项不是整体变更控制的内容

A.对可能引起变更的因素施加影响

B.在整个项目期间和整个范围内协调各种类型的变更

C.确保项目的绩效测量基准不发生变化

D.当变更实际发生时对变更进行管理

PMP考试参考答案:C

阅读本文的人还阅读了:
PMP考试报名费是多少?
2022年PMP考试时间
pmp是什么考试?
PMP认证考试的报名条件?
pmp能自己报名吗?
考pmp必须参加培训吗?
PMP退考费多少?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库