PMP考试每天一练-2022年PMP考试模拟题85
PMP考试练习题一: 对于一个具有战略意义的重要客户资源,项目经理在确认矩阵组织中资源可用性时,发现某个关键资源已调往一个内部项目,项目经理首先应该采取何种行动? For a strategically important customer resource, when the project manager identifies a resource availability in a matrix organization, it discovers that a key resource has been redeployed to an internal project, and what action should the project manager take first? A:与项目赞助人协商推迟项目 Negotiate and postpone projects with project sponsors B:要求项目管理办公室将资源重新调回项目 Request the project management Office to reassign resources to the project C:更新风险登记簿 Update the Risk register D:与职能经理协商将资源重新调回项目 Negotiate resources back to project with functional manager PMP考试答案解析:根据题意,关键资源已经被调往一个内部其他项目,项目经理应使用谈判这个组建项目团队的工具与职能经理谈判来获得这个关键资源。 PMP考试参考答案:D PMP考试练习题二: 下面哪一项属于组织过程资产? A. 组织结构 B. 组织文化 C. 共享知识库 D. 相关方风险承受力 PMP考试参考答案:C |