PMP考试每天一练-2020年PMP考试练习题178

转载者:PMP团购网      发布时间:2021/1/11        点击: 1030

PMP考试练习题一:

While preparing for a project, a project management considers how to deal with large changes that may occur during project execution, the project manager should do which of the following?

A. Discuss all changes with the project sponsor as soon as they are requested.

B. Express in the project management plan that the large changes cannot be accommodated.

C. Ensure that a change control board is established to deal with such situations if they occur.

D, Inform the project team that all changes must be approved by the project manager.

准备项目时,项目经理考虑如何处理在项目执行过程中可能发生的重大变更。项目经理应采取下列哪一项措施?

A.在项目发起人请求变更时立即与他们讨论所有变更

B.在项目管理计划中明确表示不允许有重大变更

C.确保建立变更控制委员会,在发生这种情况时立即处理

D.通知项目团队,所有变更都必须由项目经理批准

PMP考试答案解析:重大变更应该确保获得变更控制委员会的批准。

PMP考试参考答案:C

PMP考试练习题二

一个项目由三个活动组成。A活动历时5周,B活动历时6周,C活动历时7周。活动排序为A-B-C。但是,活动B的资源分配要1周,C在B活动开始1周后开始。则该项目最短工期是多少?

A:12 周

B:13 周

C:14 周

D:16 周

PMP考试答案解析:指南-6.3.2.2 确定和整合依赖关系&6.3.2.3 提前量和滞后量,如图:5+7+2=14

PMP考试参考答案:C

阅读本文的人还阅读了:
pmp考试内容有哪些?
PMP退考费多少?
PMP考试时间
pmp是英文考试吗?
pmp考试资格有学历要求吗?
东莞PMP考试地点在哪里?
pmp一年挂靠多少钱?
pmp培训远程还是面授好?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库