PMP考试练习题一: A project manager is assigned to a project and is organizing group activities to document the requirements baseline for that project. What are the group creativity techniques that can be used? A. Brainstorming and affinity diagrams B. Unanimity and plurality C. Proto typers and requirements documentation D. Benchmarking and control charts 某项目经理受命承担一个项目,并且目前通过团体活动制定该项目的需求基准。可采用何种团体活动方法? A. 头脑风暴法和亲和图法 B. 一致同意和大多数原则 C. 原型和需求文件 D. 基准和控制图 PMP考试答案解析:选项A和B都是团体活动,但是看英文能够发现题目问的是group creativity techniques团体创新技术。 PMP考试参考答案:A PMP考试练习题二 The development team observes that two major project variables are moving in opposing directions, which could put the project at risk. What tour technique should the project manager use to determine how closely related these two variables are? A. Scatter diagram B. pare to chart C. Histogram D. Variance analysis 开发团队观察到两个主要项目变量向相反方向移动,可能导致项目处于风险当中。项目经理应使用什么工具或技术来确定这两个变量是如何密切相关的? A.散点图 B.帕累托图 C.直方图 D.偏差分析 PMP考试答案解析:确定两个变量之间的关系使用散点图。 PMP考试参考答案:A |