PMP考试每天一练-2020年PMP考试练习题153
PMP考试练习题一: During user acceptance testing for the project deliverables, the customers finds one key function was not identified.What should the project manager review next with the customer? A. Responsibility assignment matrix B. Project scope statement C. Quality management plan D. Requirements traceability matrices 在用户对项目可交付成果开展验收测试时,客户发现其中一个关键功能未被识别。项目经理下一步应该与客户审查哪一项? A. 职责分配矩阵 B. 项目范围说明书 C. 质量管理计划 D. 需求追溯矩阵 PMP考试答案解析:功能没有识别出来,PM要和客户查看需求追溯矩阵,看看客户到底有没有提过这个需求。 PMP考试参考答案:D PMP考试练习题二 After indentifying a risk that will negatively impact a project, the project team contracts an insurance company to manage the risk effects, Which of the following risk strategies was used? A. Avoid B. Transfer C. Mitigate D. Share 识别到一个将对项目产生负面影响的风险后,项目团队在一家保险公司投保来管理风险影响。这使用的是下列哪一项风险策略? A.回避 B.转移 C.减轻 D.分享 PMP考试答案解析:买保险属于风险转移。 PMP考试参考答案:B |