PMP考试每天一练-2020年PMP考试练习题152
PMP考试练习题一: A project manager is assigned to a project with a rapidly changing environment. The requirements scope is difficult to define in advance, which of the following project life cycle models should assist the project manager to define small incremental improvements and deliver best value to stakeholders? A. Iterative and incremental life cycles B. Adaptive life cycles C. Predictive life cycles D. Phase-to-phase relationships 项目经理被分配管理一个具有快速变化环境的项目。需求范围难以提前定义。下列哪一个项目生命周期模型应协助项目经理定义较小的增量改进,并为干系人提供最大价值? A.迭代性和增量型生命周期 B.适应性生命周期 C.预测型生命周期 D.阶段到阶段关系 PMP考试答案解析:应对快速变化的环境,使用适应型生命周期。 PMP考试参考答案:B PMP考试练习题二 As a result of the Control Quality process, change requests are generated and approved by the change control board. What should the project manager do next? A. Evaluate the change requests with the change control board B. Schedule the implementation of the approved changes C. Evaluate the risk if the changes are not implemented D. Perform a root cause analysis to identify the sources of the changes 作为控制质量过程的结果,产生变更请求,并由变更控制委员会批准。项目经理下一步该怎么做? A.与变更控制委员会一起评估变更请求 B.安排批准变更的实施 C.评估如果不实施变更的风险 D.执行根本原因分析确定变更的缘由 PMP考试答案解析:变更请求被批准了,下一步是更新项目计划、实施变更。 PMP考试参考答案:A |