PMP考试练习题一:

All project scope deliverables are complete. However, the client insists the project is not fully complete To demonstrate project completion and accommodate the client’s outstanding issues, what should be used?

A.Project closure document

B.Product scope statement

C.Issue log

D.Project quality management plan

所有项目范围可交付成果均已完成。但是,客户坚持任务项目未全部完成。为了证明项目完工并包含客户的未解决问题,应该使用下列哪一项?

A.项目收尾文件

B.产品范围说明书

C.问题日志

D.项目质量管理计划

PMP考试答案解析:项目或阶段收尾文件包括表明项目或阶段完工的正式文件,以及用来把完成的项目或阶段可交付成果移交给他人(如运营部门或下一阶段)的正式文件。

PMP考试参考答案:A

PMP考试练习题二

After the project 'work is completed, a meeting is held with the client to. Deliver the four products. The client accepts two of the four products, and indicates that the remaining two products do not meet the requirements. Before delivering the product, which process should the project manager have following to ensure alignment with the customer’s expectations?

A. Control Quality

B. Perform Quality Assurance

C. Perform Quality Control Measurement

D. Perform Quality Audit

在项目工作完成后,与客户一起召开会议支付四个产品。客户接受四个产品中的其中两个,并表明剩余两个产品不满足需求。支付产品之前,项目经理应该遵循哪个流程来确保与客户的期望保持一致?

A.控制质量

B.执行质量保证

C.执行质量控制测量

D.执行质量审计

PMP考试答案解析:PM确保产品与客户的期望保持一致,这是控制质量。

PMP考试参考答案:A

阅读本文的人还阅读了:
pmp是什么职位的简称?
pmp是什么岗位?
本科刚毕业能考PMP吗?
南昌PMP考试地点在哪里?
PMP证书含金量到底是多少?
PMP考试含金量?
pmbok第六版免费下载
PMP远程培训多少钱?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库