PMP考试每天一练-2020年PMP考试练习题139
PMP考试练习题一: A project manager receives the results from an internal quality audit. Several project shortcomings and areas for improvement are reported. A. Implement recommendations and conduct follow up quality audit to confirm issues are resolved B. Create change requests for audit recommendations C. Use flowcharts to prioritize the shortcomings D. Perform a cost-benefit analysis 项目经理收到内部质量审计的结果。结果报告了多个项目缺点以及待改进之处。项目经理下一步应该怎么做? A.实施建议并开展跟进质量审计来确认问题已得到解决 B.创建审计建议变更请求 C.使用流程图来排列缺点的优先顺序 D.执行审计建议的成本效益分析来计算建议的价值 PMP考试答案解析:质量审计的目标在于识别项目中低效率、低效力的过程,采取后续措施纠正问题、确认已批准的变更请求的实施情况。 PMP考试参考答案:A PMP考试练习题二 Which document provides of framework for a cost estimate? A. Project management plan B. Work breakdown structure (WBS) C. Risk management plan D. Scope baseline 哪一份文件提供了成本估算框架? A.项目管理计划 B.工作分解结构(WBS) C.风险管理计划 D.范围基准 PMP考试答案解析:考估算成本的输入。 PMP考试参考答案:D |