PMP考试练习题一:

A project manager is assigned to a new product development project I a functional organization, the project team is selected from various locations according to expertise. After finding it difficult to manage project team members who are located in different locations, the project manager requests a new location to bring the team together, What technique does the project manager use to Develop Project Team?

A.Tight Marti

B.Beam building

C.Forming

D.Ground rules

项目经理被分配管理一个职能型组织里的新产品开发项目。项目团队是按照专业知识从不同地方选择的。发现难以管理分处不同地方的项目团队成员后,项目经理申请了一个新地点,将团队集合在一起。项目经理使用的是什么项目团队建设技术?

A.紧密矩阵

B.团队建设

C.形成

D.基本规则

PMP考试答案解析:将团队成员集合在一起这是集中办公,也叫紧密矩阵。

PMP考试参考答案:A

PMP考试练习题二

Based on initial estimates, a project’s most likely activity cost is US$4,000, but the best case scenario activity cost is US$3,000. In the worst case scenario, the activity cost is US$6,000 Using PERT, what is the expected activity cost?

A.US$4,167

B.US$4,333

C.US$4,666

D.US$3,883

根据初始估算,一个项目最有可能的活动成本为4,000美元,但是最好情况活动成本为3,000美元,在最坏情况下,该活动成本为6,000美元。使用PERT,预算活动成本是多少?

A.4167美元

B.4333美元

C.4666美元

D.3883美元

PMP考试答案解析:根据三点估算公式(3000+4*4000+6000)/6=4167。

PMP考试参考答案:A

阅读本文的人还阅读了:
pmp中文全称是什么?
什么是pmp项目管理?
pmp考试资格报名条件?
pmp报考条件需要什么学历?
福州PMP考试地点在哪里?
PMP证书可以挂靠吗?
PMP考试费用为什么这么贵?
pmbok6英文版下载
pmp远程好面授好,谁知道?
PMP通过率怎么样?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库