PMP考试每天一练-2020年PMP考试练习题137
PMP考试练习题一: A new project manager reviews a project’s documentation, information, and data. Concerned about project delays, the new project manager wants to identify relationships between the variables.What tool should the project manager use to determine if changes should be made to the project? A. Ishikawa diagram B. Control chart C. Histogram D. Scatter diagram 一名新项目经理审查了项目的文档,信息和数据。因为担心项目延迟,新项目经理希望识别变量之间的关系。项目经理应该使用什么工具来确定是否应该对项目进行变更? A.石川图 B.控制图 C.直方图 D.散点图 PMP考试答案解析:识别两个变量之间的关系。 PMP考试参考答案:D PMP考试练习题二 After collecting requirements and defining the project scope, the project manager realizes that there is insufficient information to establish a cost estimate. However, the project manager knows of several ongoing and past projects with similar characteristics. What should the project manager perform next? A. Analogous estimate B. Bottom-up estimate C. Rough order of magnitude estimate D. Expert judgment 经过收集需求和定义项目范围,项目经理意识到制定成本估算的信息不足。但是,项目经理了解几个具有类似特性的现有和过往项目。项目经理下一步应该执行下列哪一项? A.类比估算 B.自下而上估算 C.粗略量级估算 D.专家判断 PMP考试答案解析:估算信息不足,但是PM了解具有类似特性的项目。 PMP考试参考答案:A |