PMP考试练习题一:

During project initiation, the project manager is uncertain about a director’s role in the successful completion of a project. To understand the director’s importance, what should the project manager do next?

A.Learn the position and influence of this director by reviewing the stakeholder register

B.Review the power/interest grid

C.Have a discussion with the director on project after the project charter is approved

D.Interview the director to understand his opinions

在项目启动期间,项目经理不确定一名董事在成功完成项目中所起到的作用。若要了解该董事的重要性,项目经理下一步该怎么做?

A.查看干系人登记册了解董事的职位和影响力

B.查看权利/利益方格

C.在项目章程获得批准之后,与该董事讨论项目

D.访谈该董事了解其意见

PMP考试答案解析:干系人登记册中记录了干系人对项目的潜在的影响。

PMP考试参考答案:A

PMP考试练习题二

The project manager of an ongoing project leaves the company, and a new project manager is assigned. The sponsor asks the never project ranger to check the status of a key stakeholder's modification request. Where should the project manager find this information?

A. Project document updates

B. Change log

C. Stakeholder management Plan

D. Communications management plan

项目正在进行当中,项目经理从公司离职,任命了一名新的项目经理。发起人让新项目经理检查一名关键干系人修改请求的状态。项目经理可以从哪里找到这个信息?

A.项目文件更新

B.变更日志

C.干系人管理计划

D.沟通管理计划

PMP考试答案解析:变更日志里有变更请求的状态。

PMP考试参考答案:B

阅读本文的人还阅读了:
pmp是做什么的?
pmp是什么职位的简称?
pmp是什么意思的缩写?
PMP考试个人可以直接报考吗?
pmp报考条件大专可以吗?
沈阳PMP考试地点在哪里?
PMP证书含金量有多少?
pmp考试教材?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库