PMP考试每天一练-2020年PMP考试练习题131
PMP考试练习题一: A subcontractor is paid US$100 per hour, and reimbursed for all direct costs. In addition, the subcontractor receives a fee of US$100,000 for the delivery of completed work.What type of contract is this? A.Cost-plus-award-fee B.Cost-plus-fixed-fee C.Cost-plus-incentive-fee D.Fixed-price-incentive-fee 分包商的费用是每小时100美元,并补偿所有直接成本。另外,交付完工时,分包商还将获得100,000的费用。这属于哪一种合同类型? A.成本加奖励费用合同 B.成本加固定费用合同 C.成本加激励费用合同 D.总价加激励费用合同 PMP考试答案解析:成本加固定费用合同的构成=实际成本+固定费用。 PMP考试参考答案:B PMP考试练习题二 Three project tasks require services which the company cannot provide. To resolve this issue, what should the project manager do? A. Refer to the procurement management plan B. Initiate a project change request to use different services. C. Ask the functional manage to recommend wanders. D.Update the project schedule according to available resources. 有三个项目任务所需要的服务,公司无法提供。为解决这个问题,项目经理应该做什么? A.查阅采购管理计划 B.发起项目变更请求,使用不同的服务。 C.要求职能经理推荐供应商。 D.按照可用资源更新项目进度。 PMP考试答案解析:采购管理计划说明项目团队如何从执行组织外获取货物和服务,以及如何管理从编制采购文件到合同收尾的各个采购过程。 PMP考试参考答案:A |