PMP考试每天一练-2020年PMP考试练习题130
PMP考试练习题一: A company wants to proceed with a new financial application. After completing the make-or-buy analysis, the company reviews all vendor proposals and selects one vendor.What is the next task required to proceed with the project? A.Conduct contract negotiations B.Create a risk procurement plan C.Appeal management’s decision to outsource the project D.Document the change request 公司希望进行一个新的财务应用程序。完成自制或外购分析之后,公司审查了所有供应商的建议书,继续进行项目的下一个任务是什么? A.进行合同谈判 B.创建一份风险采购计划 C.对管理层外包项目的决定进行申诉 D.记录变更请求 PMP考试答案解析:公司评估了供应商的建议书,下一步是进行合同谈判。 PMP考试参考答案:A PMP考试练习题二 During the planning process, a project team identifies a risk of quality nonconformance prepares an action plan for this risk. To avoid nonconformance during project execution, the project manager should do which of the following? A. Risk assessment B. Risk mitigation C. Risk prioritization D. Risk transference 在规划中,项目团队识别到一个质量不合格风险,并为这个风险准备了一份行动计划。若要避免项目执行过程中的不合格,项目经理应进行下列哪一项? A.风险评估 B.风险减轻 C.进行风险优先排序 D.风险转移 PMP考试答案解析:识别到风险后,要避免项目执行过程中出现问题,应该进行风险评估。 PMP考试参考答案:A |