PMP考试练习题一:

A key stakeholder informs the project manager that critical project deliverables are not included in the scope baseline. The key stakeholder provides further details regarding the additional project deliverables

According to the scope management plan, what should the project manager do next?

A.Control scope

B.Monitor and control project work

C.Perform integrated change control

D.Validate scope

一名关键干系人通知项目经理关键项目可交付成果不包含在范围基准中。关键干系人提供额外项目可交付成果的进一步详情。根据范围管理计划,项目经理下一步该怎么做?

A.控制范围

B.监控项目工作

C.执行整体变更控制

D.核实范围

PMP考试答案解析:管理对范围基准的变更。

PMP考试参考答案:A

PMP考试练习题二

A full-time project team member leaves the company. The project manager identifies a Coiner team member with a similar skill set. However, the team member is only available on a part-time basis for this project. In addition to the project schedule, what other document should the project manager update?

A. Staffing management plan

B. Activity list

C. Communications management plan

D. Schedule baseline

一名全职项目团队成员从公司离职。项目经理确定了一名拥有类似技能集的团队成员进行替换。但是,该团队成员仅能在该项目中兼职工作。除了项目进度计划外,项目经理还应更新哪一份文件?

A.人员管理计划

B.活动清单

C.沟通管理计划

D.进度基准

PMP考试答案解析:选项A看英文就是人员配置管理计划。该计划说明将在何时、以何种方式获得项目团队成员,以及他们需要在项目中工作多久。

PMP考试参考答案:A

阅读本文的人还阅读了:
pmp英文全称是什么?
什么叫pmp?
pmp考试资格有学历要求吗?
自考本科可以考PMP吗?
厦门PMP考试地点在哪里?
pmp可挂靠吗?挂靠一年多少钱?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库