PMP考试每天一练-2020年PMP考试练习题128
PMP考试练习题一: A project sponsor implements a new document control process. This new process will delay access to information, which will lead to increased labor costs and schedule delay. How should the project manager integrate this new process? A.Use the risk management plan to evaluate the risk and report back to the project sponsor B.Propose a more efficient document control process for use on the project C.Implement the new requirements using the change management plan D.Schedule a meeting with project stakeholders for a risk urgency assessment 一个项目发起人落实一项新的文件控制流程。这项新流程将延迟对项目的访问,将导致人工成本增加及进度延迟。项目经理应该如何整合这项新流程? A.使用风险管理计划评估风险,并向项目发起人报告 B.想出更为有效的文件控制流程用于项目 C.使用变更管理计划实施心需求 D.与项目关系人安排一次会议,进行风险紧迫性评估 PMP考试答案解析:将导致人工成本增加及进度延迟,说明这是风险,排除C。 PMP考试参考答案:A PMP考试练习题二 A key user representative involved in product validation activities proposes changes to some tasks and deliverables outlined in the project's methodology. These changes would considerably impact the validation strategy defined during the planning phase.What should the project manager do first? A. Remove the key user representative from the validation team B. Include the project management office (PMO) in the discussion C. Send an e-mail to the key user representative with the agreed-upon methodology outlined in the planning phase D. Maintain authority and ensure the validation strategy is executed as planned 参与产品核实活动的一名关键用户代表提出对项目方法中所述的一些任务和可交付成果进行变更,这些变更将对规划阶段所定义的核实策略造成相当大的影响。项目经理首先应该做什么? A.将该关键用户代表从核实团队开除 B.将项目管理办公室(PM0)包含进讨论中 C.向关键用户代表发送一封电子邮件,并附上规划阶段中所述的约定方法 D.保留职权,并确保按计划执行核实策略 PMP考试答案解析:关键用户提出对项目管理方法中的一些内容进行大的变更,PM应该把PMO也包含进讨论中。因为PMO的职能是给予项目提供指导、辅导、监督,制定项目管理方法以及识别最佳实践。 PMP考试参考答案:B |