PMP考试每天一练-2020年PMP考试练习题125
PMP考试练习题一: A project manager works with stakeholders and sponsor to clarify project scope, improve the cost and define time line. The project manager prepares the kick off meeting to officially start the project.The project manager is in which process group? A.Initiating B.Executing C.Monitoring & controlling D.Planning 项目经理与干系人和发起人一起澄清项目范围,完善成本并定义时间线。项目经理准备召开项目启动大会,正式启动项目。项目经理处于下列哪一个过程组? A.启动 B.执行 C.监控 D.规划 PMP考试答案解析:启动大会kick-off meeting属于规划过程组。 PMP考试参考答案:D PMP考试练习题二 A project team learns that specific seller is in financial difficulty and could present a risk to the project. What should the project manager do next? A. Accept the risk and closely monitor the seller’s deliverables. B. Transfer the risk by adding a penalty clause to the contact. C. Mitigate the risk by obtaining insurance for the risk. D. Avoid the risk by identifying alternative sellers. 项目团队了解到某个卖方正在经历财务困难,可能会对项目产生风险。项目经理接下来应该怎么做? A.接受风险并密切监视卖方的可交付成果。 B.通过对合同增加处罚条款转移风险。 C.通过为风险购买保险减轻风险。 D.通过识别替代卖方避免风险。 PMP考试答案解析:供应商有困难,应该合作并一起克服。但也要及时监控,做好风险管理。 PMP考试参考答案:A |