PMP考试每天一练-2020年PMP考试练习题120
PMP考试练习题一: Suppliers dispute their project tasks with the project manager. During the project’s execution, this project manager is replaced with a new project manager.To manage the suppliers, which of the following tools and techniques should the new project manager use? A.Claims administration B.Integrated change control C.Contract change control system D.Records management system 供应商与项目经理对项目任务有争议。在项目执行期间,一名新项目经理代替了该项目经理。为了管理供应商,新项目经理应该使用下列哪一项工具? A.索赔管理 B.整体变更控制 C.合同变更控制系统 D.记录管理系统 PMP考试答案解析:有争议就是索赔管理。 PMP考试参考答案:A PMP考试练习题二 While resolving a project issue, the project team generates ideas about the issue that can be linked by common attributes. What technique is the project team using? A. Interrelationship diagram. B. Affinity diagram C. Multi-criteria decision analysis D. Network diagram 在解决一个项目问题的同时,项目团队产生了通过共同属性将问题直接联系起来的想法。项目经理使用的是什么技术? A.关系图 B.亲和图 C.多标准决策分析 D.网络图 PMP考试答案解析:亲和图是按照共同属性、逻辑关系将问题直接联系起来。 PMP考试参考答案:B |