以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2020年PMP考试练习题117

转载者:PMP团购网      发布时间:2020/9/4        点击: 1082

PMP考试练习题一:

Since the project schedule does not meet the time constraints, the project manager outsources the most difficult task to a provider known to be competent, bue expensive. The provider’s contract is a cost-plus-fixed-fee.Which of the following documents should the project manager update?

A.Schedule and cost management plans

B.Cost, risk, schedule, and communications management plans

C.Risk, procurement, and schedule management plans

D.Schedule, cost, risk, communications, and procurement management plans

因为项目进度不满足时间制约因素,项目经理将最困难的任务外包给一个知道其有能力但昂贵的供应商。该提供商的合同是成本加固定费用合同。项目经理应更新下列那一份文件?

A.进度和成本管理计划

B.成本、风险、进度和沟通管理计划

C.风险、采购和进度管理计划

D.进度、成本、风险、沟通和采购管理计划

PMP考试答案解析:实施采购的输出,项目管理计划更新。见PMBOK。

PMP考试参考答案:D

PMP考试练习题二

A new project manager reviews a project's documentation, information, and data. Concerned about project delays, the new project manager wants to identify relationships between the variables.What tool should the project manager use to determine if changes should be made to the project?

A. Ishikawa diagram

B. Control chart

C. Histogram

D. Scatter diagram

一名新项目经理审查了项目的文档,信息和数据。因为担心项目延迟,新项目经理希望识别变量之间的关系。项目经理应该使用什么工具来确定是否应该对项目进行变更?

A.石川图

B.控制图

C.直方图

D.散点图

PMP考试答案解析:散点图可确定变量之间的关系。

PMP考试参考答案:D

阅读本文的人还阅读了:
南京PMP考试地点在哪里?
pmp证书有含金量吗?
PMP考试报名时间?
PMP报名资格是什么?
pmp项目管理资格证书报名条件?
pmp证书含金量多少?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库