PMP考试每天一练-2020年PMP考试练习题115
PMP考试练习题一: There is a personal conflict between two members. The team members do not talk to each other and the project manager anticipates that this will have a direct effect on execution.The team members are using which of the following conflict resolution technique? A.Withdraw/avoid B.Collaborate/problem solve C.Compromise/reconcile D.Force/direct 两个团队成员之前存在个人冲突。这两名团队成员互相不说话,项目经理预计到这对项目执行产生直接影响。团队成员正在使用下列哪一项冲突解决技巧? A.撤退/回避 B.合作/解决问题 C.妥协/调解 D.强迫/命令 PMP考试答案解析:两名成员间存在冲突,但是互相不说话是在避免冲突。 PMP考试参考答案:A PMP考试练习题二 Contractors are hired during a project's initial phase. The project stakeholders approves a limited budget for this phase. The project manager knows that this phase will not require any scope changes.Which type of contract should be used? A. Firm fixed price (FFP) B. Cost plus fixed fee (CPFF) C. Fixed price incentive fee (FPIF) D. Cost plus award fee (CPAF) 承包商是在项目初始阶段聘用的。项目干系人批准了该阶段的有限预算。项目经理知道该阶段不要求任何范围变更。应该使用哪一个合同类型? A.固定总价合同(FFP) B.成本加固定费有合同(CPFF) C.总价加激励费用合同(FPIF) D.成本加奖励费用合同(CPAF) PMP考试答案解析:预算有限且范围确定。 PMP考试参考答案:A |